Bid # Project Name Estimated Completion Date Original Award Ward
7490 Downtown Pedestrian and Bicycle Improvements
State-Aid Project No. ATPL-5058(96)
01/27/21  $1,233,881.62 1,2,3,7
7631 Magnolia Ave. Improvements from Buchanan to Banburry
Federal Aid Project: STPL-5058(102) 
01/13/21  $13,138,339.25 6,7
7641 2018-2019 SB-1 Maintenance and Traffic Improvements   01/29/21  $5,238,400.00 1,2,3,4,5,6,7
7696 Iowa Avenue Improvements from Martin Luther King to University 02/26/21  $4,769,690.00 2

7727

City-Wide Bicycle and Pedestrian Improvements

03/11/21

$886,763.00

1,2,3

7736

City-Wide Curb, Gutter, Sidewalk and ADA Ramp Repairs

02/19/21

678,404.70

1,2,3,4,5,6,7

7741

Campbell Ave Sewer Replacement and City-Wide Manhole Rehab and Replacement

TBD

$898,300.00

4,5,6,7

7756

Phoenix Storm Drain Diversion

TBD

$567,729.00

1

7765

Adair Ave and Bonita Sidewalk Improvements

TBD

$392,355.00

6, 7

7781

2018-2019 CDBG Ward 5 Improvements for Hayes St, Taft St and Myers St

TBD

$292,228.00

5


 

Planned Construction Projects

Below you will find a list of planned Capital Improvement Projects.
This list was last updated on 3/12/2021.

Bid # Project Name Estimated Completion Date Estimated Cost Ward
7542 La Sierra Sidewalk Improvements Winter 2022 $2,100,000 7
7631 Magnolia Avenue Improvements (Buchanan to Banbury) April 2021 $15,500,000 6, 7
7696 Iowa Avenue Improvements (MLK to University) April 2021 $5,860,000 2
7705 FY 19-20 SB-1 Maintenance Improvements, Phase 1 September 2021 $3,150,000 1, 4, 5, 6, 7
7706 FY 19-20 Arterial and Minors Maintenance, Phase 1 December 2021 $4,730,000 5, 6, 7
7707 FY 19-20 Arterial and Minors Maintenance, Phase 2 February 2022 $4,210,000 3, 4, 5
7708 FY 19-20 Arterial and Minors Maintenance, Phase 3 March 2022 $3,230,000 1, 2
7718 Monroe MDP Line E Storm Drain Project/Gratton Street Improvement TBD $11,500,000 5
7781 FY 18-19 CDBG Ward 5 Street Improvements April 2022 $380,000 5
7788 FY 19-20 CDBG ADA and Street Improvements May 2021 $1,120,000 1, 2, 3, 6, 7
7823 Canyon Crest Ave Bus Stop and Maintenance September 2021 $1,790,000 1, 2
TBD Sewer Mains Construction on MLK Blvd. and Canyon Crest Dr. Winter 2021 $1,500,000 2
TBD FY 19-20 SB-1 Traffic Improvements Spring 2022 $1,100,000 All
TBD FY 20-21 SB-1 Maintenance Improvements Spring 2022 $5,000,000 1, 2, , 4, 5, 7
TBD FY 20-21 CDBG Ward 2 Street Improvements Spring 2022 $400,000 2
TBD FY 20-21 Arterial and Minors Maintenance, Phase 1 Spring 2022 $3,250,000 1, 2, 3, 4
TBD FY 20-21 Arterial and Minors Maintenance, Phase 2 Late Summer 2022 $3,350,000 4, 5, 6, 7
TBD FY 20-21 SB-1 Traffic Improvements Late Summer 2022 $1,000,000 1, 2, 6
TBD FY 19-20 SB-1 Maintenance Improvements, Phase 2 Late Summer 2022 $2,560,000 2, 3
TBD Van Buren Blvd. Sewer Construction from Wood Rd. to King Ave. Winter 2023 $11,000,000 4
TBD Van Buren Blvd. widening from Jurupa Ave. to the Northerly City Limits Spring 2023 TBD 3, 7
TBD SR-91/Adams Street Interchange Reconfiguration TBD $42.4M to $56.8M 4, 5
TBD MDP Line E-1 Storm Drain Project TBD $5,100,000 5
TBD Monroe Channel Storm Drain Project TBD $12,000,000 5
TBD Third Street Grade Sep Project TBD $55,500,000 1
TBD MDP Line D Storm Drain Project TBD $3,600,000 1