:: La Sierra Freeway Interchange Replacement
Cost: $38,000,000
Status: Completed
Start Date : Fall 2007
End Date : Summer 2009
Neighborhood: La Sierra - La Sierra South
Maps: Aerial Map
Contact: 951-826-5670

Description

Construction of this $38 million project began in October 2007 and is scheduled for completion in July 2009. The project will extend from Diana Avenue/Montlake Drive to Indiana Avenue. Approximately 3000 feet along State Route 91 will also be affected by the project.

Construction of the project will enhance the capacity and operation of the interchange. Both the freeway and the railroad bridges are being replaced with six lane structures including dual left turn lanes. The freeway ramps will be widened to three lanes. The areas surrounding the ramps will be landscaped.

La Sierra Avenue will remain open to traffic during construction; however there may be short periods of time when traffic lanes will be closed. Periodic night-time freeway closures and limited ramp closures are expected. Access to properties along the project will be maintained during construction.

 
City Engineering
La Sierra Interchange Links
Construction Video Video

View video on the La Sierra Interchange project

Construction Projects
Construction Projects
Riverside Renaissance Public Works Projects
Public Works Hours
7:30 a.m. - 5:30 p.m.
Monday - Friday
3900 Main Street - 4th Floor
Click for Map
Closed on Weekends and
Major Holidays
951-826-5341
To Report a Problem
Dial 311 or visit the city's 311 Call Center
to report a problem.