Project Summary

Cost: $786,865.00
Status: Completed
Start Date : 09/04/2012
End Date : 12/13/2012
Ward : 3
Contact:
  TBA Brandi Becker
    Senior Administrative Analyst
    951-826-2306

Description

The project entails maintenance improvements of various streets including Magnolia Avenue, Elizabeth Street, Merrill Avenue, De Anza Avenue, and Sunnyside Drive, and generally includes, but not limited to, the reconstruction of asphalt pavement, concrete sidewalks, driveways, wheelchair ramps, curb and gutter; adjustment of water meters boxes, water valve covers, gas ETS covers, and manholes; replacement of traffic loops and striping; and installation of signs.


Master Plans
Construction Projects
Construction Projects
General Information
Address:
3900 Main Street - 4th Floor
Riverside, CA 92522

Phone: (951) 826-5341

Hours
Monday - Friday 7:30am - 5:30pm
Closed Major Holidays
City of Riverside  |  Explore Riverside  |  At Home in Riverside  |  Seizing Our Destiny
Copyright © 2014 City of Riverside | Accessibility Policy | Website Disclaimer | Privacy Policy
Facebook: Like the City of Riverside LinkedIn Twitter YouTube: Subscribe to the City of Riverside RSS: Stay up-to-date with the latest news from the City of Riverside GovDelivery: Receive email alerts from the City of Riverside GTV: City of Riverside's television channel Outlook E-News
Printed from: http://www.riversideca.gov/publicworks/engineering/bid7063.asp