Orrenmass School Footpath Access Project

Before Construction

During Construction

After Construction

  • bid 6980 during construction photo
  • bid 6980 during construction photo
  • bid 6980 after construction photo

Project Summary

Cost: $237,721.08
Status: Completed
Start Date : 06/25/2012
End Date : 09/25/2012
Ward : 1
Contact:
  TBA Brandi Becker
    Senior Administrative Analyst
    951-826-2306

Description

The project entails construction of PCC sidewalk along the south east side of Dorset Drive from Fillmore Street to Durham Drive, construction of PCC sidewalk along both sides of Layton Court and construction of PCC sidewalk along both sides of Wallingham Drive from Dorset Drive to Millard Drive. The project also includes construction of wheelchair ramps, sidewalk retaining curbs, reconstruction of existing driveways, reconstruction of fences to behind right of way,

Master Plans
Construction Projects
Construction Projects
General Information
Address:
3900 Main Street - 4th Floor
Riverside, CA 92522

Phone: (951) 826-5341

Hours
Monday - Friday 7:30am - 5:30pm
Closed Major Holidays
City of Riverside  |  Explore Riverside  |  At Home in Riverside  |  Seizing Our Destiny
Copyright © 2014 City of Riverside | Accessibility Policy | Website Disclaimer | Privacy Policy
Facebook: Like the City of Riverside LinkedIn Twitter YouTube: Subscribe to the City of Riverside RSS: Stay up-to-date with the latest news from the City of Riverside GovDelivery: Receive email alerts from the City of Riverside GTV: City of Riverside's television channel Outlook E-News
Printed from: http://www.riversideca.gov/publicworks/engineering/bid6980.asp